How to Setup Machine Layout for Basic Woven Shirt in Clothing Industry?

Woven Shirt Sewing Production Line Layout in Apparel Industry

Machine layout plan is always a key factor for higher production. If the total plan is executed perfectly then it will easy for the production team to meet shipment date without any hassle. As its importance, this article has presented a well-tested machine layout plan for woven shirt or formal shirt or casual shirt or basic shirt. 

You may follow: 

1. Major Components of a Basic Shirt | Operation Breakdown of a Basic Shirt 

2. Different Parts of a Jeans Pant | Operation Breakdown of Jeans Pant 

3. How to Setup Machine Lay Out for Jeans Pant in Apparel Industry?

4. Cutting Cost Calculation Formula | Fabric Cutting Cost in Bangladesh 

5. Apparel Checking Methods | Quality Checking List of Apparel Industry 

6. Apparel Packing Materials | Apparel Packaging Cost Calculation Formula  

7. What is Shipment | What is Shipping | International Shipping Process Flow Chart

8. Steps of Apparel Inspection | Apparel Inspection Cost

9. What is Bra or Brassier? | 35 Different Types of Bra with Names and Pictures 

10. List of Top 100 Clothing Brands in the World 

Machine Layout for Woven Shirt in Apparel Manufacturing Sector

We will make calculations for body and collar-cuffs-sleeves separately @150pc per hour. Body processes operations are shown here. Processes are allocated to operators so as to make a layout for body processes.

Machine Lay Out Plan for Shirt Body

SL No.Name of OperationsMachine RequiredStandard TimeOperator Allocation
01Attach top center to left front4-ndl double chain stitch machine24”Operator-1
02Hem pocket mouth1-ndl lock stitch with thread trimmer12”Operator-2,3
03Fold pocketManual42”Operator-4,5
04Attach pocket1-ndl lock stitch with thread trimmer40”Operator-2,3
05Hem right front button stand1-ndl lock stitch with hemmer folder24”Operator-6
06Cut & fold labelLabel cutting & folding machine3”Operator-7
07Attach label to under yoke1-ndl lock stitch with thread trimmer16”Operator-7
08Back yoke attach sewing1-ndl lock stitch with thread trimmer24”Operator-8
09Back yoke top stitch1-ndl lock stitch with thread trimmer19”Operator-9
10Shoulder join1-ndl lock stitch with thread trimmer46”Operator-10, 11
11Top stitch on shoulder join1-ndl lock stitch with thread trimmer24”Operator-12
12Attach sleeves2-ndl 5-thread safety stitcher48”Operator-13, 14
13Side seam2-ndl feed of the arm machine46”Operator-15, 16
14Collar attach sew1-ndl lock stitch with thread trimmer40”Operator-17, 18
15Collar attach stitch1-ndl lock stitch with thread trimmer40”Operator-19, 20
16Hem body bottom1-ndl lock stitch with thread trimmer with hemmer foot24”Operator-21
17Attach cuffs1-ndl lock stitch with cuff folder48”Operator-22, 23
18Button sewingButton sewing machine38”Operator-24, 25
19Buttonhole sewingButtonhole sewing machine36”Operator-26, 27
Total standard time for body processes594”

Average Process Time Calculation Method

Average process time,
= (594/19)
= 31.26”

Calculation of BPT, UCL, LCL, Organization Efficiency & Production Target Per Hour

Production target per hour with 27 operators,
= {(27×3600×0.85)/594}
= 139pcs per hour

Again,
Bottleneck time= 26 second,

So,
Production per hour,
= (3600/26)
= 138pcs per hour.

Now,
Basic pitch time (BPT) is,
= (594/27)
= 22”

Again,
Upper control limit (UCL) is,
= (22”/0.85)
= 25.88”

Again,
Lower control limit (LCL) is,
= {2 × (BPT-UCL)}
= (44-25.88”)
= 18.12”

Now,
Organization efficiency is,
= (BPT/Bottleneck time)
= {(22”/26”) × 100}
= 84.66%

Again,
Direct productivity is,
= (138/27)
= 5.11 pcs per operator per hour

Machine Lay Out Plan for Shirt Collar, Cuffs and Sleeves

SL No.Name of OperationsMachine RequiredStandard TimeOperator Allocation
Collar Processes
Fp-1Fuse interliningFusing press6”Operator-Fp-1
Clr-2Sew collar1-ndl lock stitch with thread trimmer24”Operator-1
Clr-3Cut collar tip & turnManual22”Operator-2
Clr-4Form collarCollar forming machine20”Operator-3
Clr-5Press collarManual20”Operator-4
Clr-6Top stitch collar1-ndl lock stitch with thread trimmer16”Operator-5
Clr-7Sew collar bottom1-ndl lock stitch with thread trimmer8”Operator-5
Clr-8Trim collar bottomCollar contour trimmer6”Operator-6
Fp-1Fuse interlining to bandFusing press6”Operator-Fp-1
Clr-9Feel or roll band1-ndl lock stitch with thread trimmer18”Operator-6
Clr-10Collar band attach sewing1-ndl lock stitch with thread trimmer24”Operator-7
Clr-11Turn bandManual10”Operator-8
Clr-12Collar band attach stitch1-ndl lock stitch with thread trimmer18”Operator-9
Clr-13Cut band bottomOver lock machine6vOperator-9
Clr-14Mark 3-point on collarManual12”Operator-8
Cuff Processes
Fp-1Fuse interliningFusing press12”Operator-Fp-1
Cf-2Fell or roll cuff1-ndl lock stitch with thread trimmer18”Operator-10, 11
Cf-3Sew or run stitch cuffs1-ndl lock stitch with thread trimmer30”Operator-10, 11
Cf-4Fold insideIron or vacuum board8”Operator-12
Cf-5Turn cuffsManual or iron12”Operator-12
Cf-6Form cuffsCuff forming machine24”Operator-13
Cf-7Top stitch cuffs1-ndl lock stitch with thread trimmer18”Operator-14
Cf-8Cuff pair matchManual6”Operator-15
Sleeve Processes
Slv-1Sew under placket to sleeve1-ndl lock stitch with thread trimmer18”Operator-15
Slv-2Fold upper placketManual24”Operator-16
Slv-3Attach sleeve placket1-ndl lock stitch with thread trimmer36”Operator-17, 18
Total standard time for collar, cuff & sleeves422”

Average Process Time Calculation Method:

Average process time,
= (422/24)
= 17.58”

Calculation of BPT, UCL, LCL, Organization Efficiency & Production Target Per Hour

Production target per hour with 19 operators,
= {(19×3600×0.85)/422}
= 143pcs per hour

Again,
Bottleneck time= 24 seconds,

So,
Production per hour is,
= (3600/24)
= 150pcs per hour

Now,
Basic pitch time (BPT) is,
= (422/19)
= 22.21”

Again,
Upper control limit (UCL) is,
= (22.21”/0.85)
= 26.13”

Again,
Lower control limit (LCL) is,
= {2 × (BPT-UCL)}
= (44.42-26.13”)
= 18.29”

Now,
Organization efficiency is,
= (BPT/Bottleneck time)
= {(22.21”/24”) × 100}
= 97.66%

Again,
Direct productivity is,
= (150/18)
= 8.33 pcs per operator per hour